News

TOPPING-OUT THE FIRST 26-FLOORS TOWER IN THE ORIGAMI AREA – VINHOMES GRAND PARK PROJECT

On the morning of March 29, 2021, CENTRAL together with Vingroup Investor and MV Vietnam Real Estate Joint Stock Company held the topping-out ceremony of two towers S7.01 and S7.05, Vinhomes Grand Park project – The Origami subdivision in Long Thanh My Ward, District 9, HCMC.

The ceremony is honored to have the presence:

  • From Investor – Vinhomes Construction Joint Stock Company:
    • Le Van Viet – Site Director
    • Nguyen Van Thuc; Mr. Hua Hong Phu – Chief Supervision Consultant
  • From Central:
    • Nguyen Thien Thuat – Project Director
    • Chau Van Bang – Project Director of MEP
    • Thap Ba Thanh Nhan; Mr. Duong Hong Cong – Chief Commander
    • Truong Minh Toan – Chief Commander of MEP
Project Management Board of Investor and Contractor doing the ritual of the topping-out ceremony

CENTRAL assumed the role of General Contractor of 4 towers S7.01; S7.02; S7.03; S7.05. Up to the present time, the construction progress has exceeded the schedule by 1.5 months. Specifically:

  • Building S7.01 and S7.05: Topping-out
  • 02 and S7.03: Expected to top-out in early May 2021
4 Towers S7.01; S7.02; S7.03; S7.05 on the topping-out day

Giving priority to ensure quality and safety while speeding up the construction, CENTRAL Executive Committee confidently handed over 4 towers ahead of time, meeting the expectations for investors.

 The Management Board was joyful on the day of topping out