Entering the beginning of 2020, there will be many outstanding events at the Northern CENTRAL site. On the morning of January 11, 2020, CENTRAL together with the investor of Vingroup organized the topping-out ceremony of 3 towers H1, H2, H6 – Vinhomes Smart City Project in Tay Mo, Dai Mo, Nam Tu Liem, Ha Noi city.
Along with the presence of SMB of the project.
Vinhomes Smart City is located on the axis of Thang Long Avenue – a prime location, where the intersection of a series of important roads, railways. Vinhomes Smart City aims to become a smart, modern city that is the focal point of every destination of the West of the capital.
In this project, CENTRAL is the only General Contractor with the role of structural construction, finishing, and MEP. Three towers with 34 floors and 1 basement. Gangform formwork construction technology and Acotec wall panels are applied in construction.
Construction of three towers H1, H2, and H6 was started by CENTRAL in March 2019, and up to now, 3 buildings have been ahead of schedule compared to the plan of the Investor, topping out the roof with 2.5 months in advance. The topping out event is not only a milestone marking the project construction process but also marks the maturity of a team of experienced, overcoming difficulties, connected to complete the work. The estimated time of handing over to the Investor is August 2020.
Immediately after the topping-out ceremony, the BOD had a year-end meeting with the SMB of the project and also sent Tet gifts to the staff.
Some featured photos in the ceremony: