On the morning April 26, 2019, Investor Phuc Dong Housing Development and CENTRAL to organized the Topping Out Ceremony of Hope Residences.
The opening Topping Out Ceremony
The ceremony was honored to welcome:
– Owner’s representative: Mr Nguyen Anh Tuan – D.CEO, Mr. Do Hai Minh – D.CEO
-The main Contractor representative: Mr Vu Duc Tai – Executive Director, Mr Tran Dang Khoa – Project Director, Mr. Trịnh Quý – Project Director (MEP); Mr Nguyen Thai Ha – Site Manager in common with partner, supervision consultants, supplier and local government.
Information of project:
– Location: Long Bien Dictrict, Ha Noi City
– Project scale: 2 basements with area of 2ha/basement, 5 21-story towers. Total construction floor area is 200.000m2
The value of the contract: 1,600 billion
-Form of contract: general contractor D&B
Hope Residences Project
The Hope Residences Site Management Board has set a construction record of completing foundation and 2 basements in 4 months. Construction of the body reached an average speed of 4 days/floor. This achievement mark an important milestone for the outstanding maturity of a team of 80 Supervisors, create a solid foundation for brothers and sisters to conquer all challenges ahead confidently.
BOD of PHUC DONG & CENTRAL had a photo with Site Management Board of Hope Residences
Representative of the Investor, Mr. Nguyen Anh Tuan – D.CEO noted the achievements and thanked the CENTRAL brothers for their contributions and efforts.
Mr Nguyen Anh Tuan – D.CEO PHUC DONG gave his speech
Mr. Nguyen Thai Ha – Site Manager sincerely thanked to all staff in Site Management Board of Hope Residences for their cooperating and determination to complete the project objectives successfully. He also shared that many of the brothers have become more mature when they have the opportunity to experience and challenge during the construction process, since then they will be promoted to higher positions in other CENTRAL projects.
Site Management Board of Hope Residence was very happy in the Topping Out Ceremony
With the enthusiasm of youth, the constant fighting spirit of a whole team of Site Management Board, who are paying attention to construction to complete MEP to hand over in 12/2019 – withdraw 3 months shorter than the contract progress.