From the evening of September 8th, 2024 to the morning of September 9th, 2024, the Central’s PMB of Olalani River Side Towers constructed a batch of concrete for the B3 basement, locked the B3 basement floor of the 2 towers B1.1 & B1.2 after 3 months of commencement, exceeding the plan 05 days ahead of schedule set by the Investor.
PROJECT INFORMATION
Project name | : | Olalani Riverside Towers |
Investor | : | Sun Group |
Address | : | Tran Hung Dao Street, Son Tra District, Da Nang City |
Scale | : | 03 twin towers from 24 to 30 floors with 1,300 apartments |
CFA | : | 135.000 m2 |
Olalani River Sde Towers project with a depth of 03 basements up to -14.15m, and an area of 2 basements of nearly 10,000m2. The project uses 2 shoring systems, and solid construction by the open-cut excavation method to withstand high groundwater and tidal pressure due to the project’s location close to the river surface. This is a big challenge for the Central’s PMB with handling experiences as well as complying with strict construction measures.
According to the plan, the project will finish the basement floor by mid-November 2024. This is an important milestone, demonstrating the non-stop and professional working spirit of Central engineers. Congratulations to the PMB and hope that the team will continue to promote this enthusiastic spirit./.