CENTRAL TOPPED OUT THE TROPICAL, VINHOMES GRAND PARK PROJECT, DISTRICT 9, HO CHI MINH CITY

On the morning of December 04th, 2023, Central Construction Joint Stock Company cooperated with Vingroup to organize the topping out ceremony of The Tropical, Vinhomes Grand Park project, District 9, Ho Chi Minh City.

The topping out ceremony took place with the presence of distinguished guests:

On the side of Investor:

  • Mr. Bui Ngoc Cuong – Executive Director
  • Mr. Le Xuan Vinh – Project Director
  • Mr. Mai Hoang Phuong – Project Director

On the side of Central:

  • Mr. Nguyen Bao Khanh – Senior Site Manager
  • Mr. Bui Van Cong – Site Manager

Together with representatives from construction units, subcontractors and employees of all parties.

Representatives of the parties took photos at the topping out ceremony of The Tropical, Vinhomes Grand Park project
Four towers S12.01 – S12.02 – S12.03 – S12.05 of The Tropical at the topping out ceremony

PROJECT INFORMATION:

Project Name:Vinhomes Grand Park – The Tropical
Form of contract:Main contractor
Scale:2 basements and 4 towers S12.01 – S12.02 – S12.03 – S12.05 with 34 to 39 floors
CFA:292.000 m2
Duration:23 months

In Vinhomes Grand Park urban area, CENTRAL has constructed almost the whole area with 12 towers in 3 subdivisions: The Rainbow, The Origami & The Tropical; 357 villas in The River Park and 5 towers in Masteri Centre Point.

The Tropical is a central zone of Vinhomes Grand Park project that conveniently connects and inherits surrounding modern facilities including Vincom Mega Mall, Rodeo Shopping Avenue, VinBus bus station,… promises to creat high-class resort life, promoting the value of the area in the future.

Perspective of The Tropical

At the ceremony, on behalf of the Project Board of Directors, Mr. Nguyen Bao Khanh – Senior Site Manager thanked partners and subcontractors for coordinating the construction work. Especially, during the construction process, PMB has made efforts to achieve more than 3,000,000 hours of safe labor and topped out the S12.01 tower on schedule. In addition, Central commits that in the near future, the finishing works will be gradually completed and handed over to the Investor with the best quality products.

Central’s PMB receives the certificate for 3,000,000 hours of safe labor